» Event Registration Form

  » APACA Events Calendar
  » View Links

  » New Links

  » Hot Links
  » View Listings

  » Search Listings
BENEFITS OF ASPHALT
VISITOR'S SIGN IN
APA MEMBER'S LOGIN
     Sunday, July 06, 2008

Sully-Miller Provides Paving Expertise For New, Expanded Mercury Air Terminal at LAX

By Tammy Boone


(Above) Sully-Miller paving new terminal parking lot.

For a number of years now Sully-Miller Contracting Company has been involved with a variety of construction projects at Los Angeles International Airport (LAX). One that is nearing completion is paving work for the new Mercury Air Terminal, an expanded, higher tech version of the terminal being constructed next to the old terminal, which has been bulldozed. The private terminal is typically used by corporate executives, government officials, foreign heads of state, and movie stars, such as John Travolta, who either fly their own planes or just want to board their private jet out of view of the crowds at LAX.

Sully-Miller has been working for general contractor The RMS Group on this project since November 2006 and expects to be completed in March of this year. Sully-Miller's scope on this project doesn't involve any demolition or export. On the land side of the terminal, the company's 11-man crew poured the concrete curbs, gutters and sidewalks for the parking area, and completed the asphalt paving and striping as well. The parking lot has an area of 50,000 square feet, and Sully-Miller poured 3,200 feet of curb, curb and gutter and sidewalk. The company also had a 4-5 man crew complete the fine grading for the parking lot prior to paving.

On the air side of the terminal, the entire ramp area—or tarmac—has been reconfigured. Prior to Sully-Miller completing the asphalt paving, the old pavement was removed, new storm drains and utilities were installed, and the ramp was graded. Complicating the paving process somewhat was that different sections of the ramp had different sub-grade conditions, depending on the use for the are. For instance, Sully-Miller placed asphalt pavement over existing concrete in some areas, but in others they placed FAA approved P401 asphalt paving. Over the period of the project, there were some problems with the sub-grade in areas, and when the specifications changed calling for parts of the sub-grade to be cement-treated, Sully-Miller completed that portion of the job.


(Above) Roller compacting newly paved parking lot.

According to Bill Grider, Senior Estimator/Project Manager, a more recent challenge on the project has been the weather.  In order for Sully-Miller to complete the next section of paving, they need to wait for the sub-grade to dry out. Bill says that since Christmas, the area has experienced quite a bit of rain, with more in the weather forecast. Once the next section is dry enough to pave over, Sully-Miller crews will place 4 inches of P401 over a 9-inch CalTrans mix base course.

Another challenge on this project has been coordinating the phasing with the airport security. The RMS Group has installed k-rail perimeter fence that is tied down to create a secure area for the terminal. The terminal has been active the entire time during the construction process, so the perimeter is constantly being moved to accommodate the construction process.

Bill says that the phasing on this project has meant that Sully-Miller hasn't had to work any nights.


(Above left) Sully-Miller paving new parking lot at the Mercury Air Terminal. (Above right) Perimeter fence relocation between phases one and two.

In phase one of the asphalt paving, Sully-Miller's crew of 12 placed 25,000 square feet of P401. In the second phase, which is nearing completion, the crew is placing 75,000 square feet of P401. 

Paving equipment on the project includes: a Terex Cedarapids 551 Paver; a 10-12 Ton Ingersoll-Rand Vibratory Roller; an Ingersoll-Rand DD 110 Vibratory Roller; a 10-12 Ton Caterpillar RTR, and a Massey-Ferguson 4-Wheel Drive Skip Loader.

One of the issues contributing to the length of this project is that the owner replaced the design engineer early on in the project. Sully-Miller's contract on the project is about $3.5 million. 


Pouring curb for new terminal parking lot.

Besides Bill, others leading the work for Sully-Miller on this project are: Mike Love, General Superintendent; Donald Barba, Paving Superintendent, John Flores, Concrete Superintendent; Chuck Piper, Grade Forman, and Jose Rios, Grade Foreman.

Bill oversees projects for private sector clients, one of which is The RMS Group. "We do a fair amount of work with them and follow them around to where that work is," Bill says. Those projects are typically in Orange, Los Angeles and Riverside Counties.

Bill Grider is currently overseeing jobs for private sector clients in Malibu, LA based movie studios, and projects at Long Beach Airport. Much of what he oversees is for companies with "B" Permits in the Los Angeles Basin.


(Above, Left to Right) Tim Owens, Greg Barba, David Gutierrez, Alfredo Haro, Harold McDonald, Gilbert Alvarez, Joe Fierro, Donald Barba, Juan Valadez.


(Above) New Mercury air terminal from the air side ramp.

Sully-Miller Contracting Company is part of the world's leader in road construction, the Colas group, and has been servicing Southern California since 1923 and is celebrating their 85th anniversary this year. Sully-Miller has the capability to offer its customers a complete range of materials and services suitable for infrastructure construction and maintenance.

For additional information look online at www.sully-miller.com or call (714) 578-9600

home : contact : about : faq : workshop/events : links : classifieds : public affairs : benefits of asphalt : visitors : members